The AD Digestor cleaning and inspection process
The planning and preparation work for a digester clean project is a critical part of the process, to ensure the safest, least disruptive and most cost-effective approach. Process Safety must be incorporated through every stage of the project based on the site's unique characteristics.
On this large pharmaceutical manufacturing site, Alpheus's approach involved carrying out the three cleans and inspections in succession to allow the transfer of biomass between tanks, and for learnings to be carried through to subsequent cleans to maximise efficiency. This ensured no disruption to production and avoided temporary storage costs.
Each digester can house 660,000 gallons of liquid waste (3000m³), so this is no mean feat. The following process was carried out for each tank:
- Tank Empty
- Isolation of tank
- Pre-inspection Tank Purge (Nitrogen and Stormwater)
- Scaffolding for cleaning
- Tank Clean
- Tank Inspection (using drones instead of scaffolding)
- Remove scaffolding
- Post-inspection Tank Purge (Nitrogen and Stormwater)
- Transfer of Biomass from between tanks
With the last digester in the final commissioning stage, the project is on target to be completed on time and within budget with no disruption to production. 15-year inspection certificates have been issued for all three tanks ensuring optimal performance and that insurance requirements are met.
If not managed properly these projects can pose significant risks to safety and health, and costs can escalate if there are unplanned disruptions. Each Anaerobic Digestion (AD) plant is different, so it is important to factor in all variables to devise the safest and most effective approach. It is our approach to such projects that sets us apart, to give customers peace of mind from both a cost and safety perspective.