Project highlights
Alpheus has delivered numerous projects during the contract to meet the client’s expansion needs and to ensure high standards of efficiency, safety and compliance – working with key as required. Examples include:
Treatment Process Improvements
A bespoke design with pre-treatment stages was proposed and bench-scale tests were carried out to obtain pre-funding. Agreement was reached with the environmental regulator SEPA and pilot trials were then carried out for an extended period to determine the potential impact of toxicity and nutrient deficiency from the pharmaceutical effluent on this process.
Client Support
Alpheus assisted with a capital tendering process for the Client, assessing the technical aspects of different designs and, ultimately, took the role of Client representative during the upgrade project.
Optimised manpower
By reducing manned hours on-site from 24/365 to 12/365 (with call-out), plant operators benefit from enhanced levels of supervision. This enables increased levels of maintenance under permit-to-work and process management support and advice while also reducing higher-risk anti-social hours and lone working.
Biogas Production
Specific projects, such as the focused optimisation of biogas production, continue to yield significant gains. This has required research into the composition of the feed and targeted supplementation of trace nutrients, optimisation of process conditions and alignment of equipment servicing with periods of low production to reduce flaring.
Odour Control Upgrades
The site had longstanding regulatory issues with odour control. Following an investigation by Alpheus into underlying reasons, the root cause was identified as a site-specific chemical reaction between two waste streams. By pre-treating the waste streams independently, we helped the client avoid the considerable cost of installing and operating an activated carbon filtering system.
Asset Lifecycle Extension
Manufacturers of process equipment often place unrealistic maintenance requirements in their operating manuals to reduce their liability in the event of failure. For example, fitting a gas holder membrane with a manufacturer-specified 5-year service life would have negated the return investment. However, Alpheus devised a new application for a product to continuously monitor membrane condition which allowed the asset’s use to extend well beyond the 5 years, and to plan for its eventual replacement.